Components
COMPONENTS
ILLUSTRATION
*1 |
HEADLIGHT LEVELING SWITCH |
*2 |
INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY |
Removal
REMOVAL
PROCEDURE
1. REMOVE INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
Click here
2. REMOVE HEADLIGHT LEVELING SWITCH
(a) Using a screw driver with its tip wrapped in protective tape, disengage the claws to remove the headlight leveling switch. |
|
Inspection
INSPECTION
PROCEDURE
1. INSPECT HEADLIGHT LEVELING SWITCH
(a) Voltage Check.
(1) Connect a positive (+) lead from the battery to terminal 1 (B) and a negative (-) lead to terminal 4 (E). |
|
(2) Measure the voltage according to the value(s) in the table below.
Standard Voltage:
Tester Connection |
Condition |
Specified Condition |
---|---|---|
2 (T) - 4 (E) |
0 |
9.5 to 10.2 V |
1 |
8.1 to 8.8 V |
|
2 |
6.6 to 7.4 V |
|
3 |
5.2 to 6.0 V |
|
4 |
3.8 to 4.5 V |
|
5 |
2.4 to 3.1 V |
HINT:
(b) Illumination Inspection.
(1) Apply battery voltage to the headlight leveling switch and check that the switch illuminates. OK:
HINT: If the result is not as specified, replace the headlight leveling switch. |
|
Installation
INSTALLATION
PROCEDURE
1. INSTALL HEADLIGHT LEVELING SWITCH
(a) Engage the claws to install the headlight leveling switch. |
|
2. INSTALL INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
Click here
Toyota CH-R Service Manual > Fog Light Assembly: Reassembly
REASSEMBLY
CAUTION / NOTICE / HINT
HINT:
Use the same procedure for the LH and RH sides.
The procedure described below is for the LH side.
PROCEDURE
1. INSTALL FOG LIGHT BULB
(a) Turn the fog light bulb in the direction indicated by the arrow shown in
the illustration, and ...
Toyota CH-R Service Manual > Front Stabilizer Bar: Inspection
INSPECTION
PROCEDURE
1. INSPECT FRONT STABILIZER LINK ASSEMBLY
(a) Inspect the turning torque of the ball joint.
(1) Secure the front stabilizer link assembly in a vise using aluminum
plates.
NOTICE:
Do not overtighten the vise.
(2) Install the nut to the front stabiliz ...